No Results Found

The page you requested could not be found. Try refining your search, or use the navigation above to locate the post.

Here you can find some conceptualizations for Phase I of the preservation of the Morris Island Lighthouse. Plans were provided by the Hayward-Baker Company.

Changes to the original Phase I plans needed to be made before the actual construction. For photos of the Phase I preservation construction, see the photo gallery below.

The base of the lighthouse will be surrounded by a cofferdam composed of circular sheet piles. This drawing is view looking down from above the lighthouse.

The base of the lighthouse will be surrounded by a cofferdam composed of circular sheet piles. This drawing is view looking down from above the lighthouse.

Grout will be injected beneath the lighthouse to stabilize the foundation. The view is looking down from above into the lighthouse's foundation.
This drawing shows section B-B through the drawing above. The view is looking across the base of the lighthouse.
Phase I - In May 2007, work began on the first phase of the lighthouse stabilization. The contractor, Taylor Brothers Marine Construction, from Beaufort, NC, drove the sheet piles that formed a cofferdam around the base of the lighthouse. The contractor worked all through the fall and winter to complete the work. His jack-up-barge can be seen from a great distance while it sits next to the lighthouse to drive the piles. All types of monitoring devices were installed inside and outside the lighthouse to help monitor the conditions as the piles were vibrated down into the sand. A local company, WPC, provided this part of the monitoring for the contractor. The devices monitored cracks for potential growth, possible lean, and general vibration during daily work. All of the windows in the lighthouse have no glass and the birds love to stay inside and even raise their young if not disturbed. The Phase I effort was completed in March of 2008, with a cost of just over $3 million.

Aerial photos were taken by Mr. Larry Workman.

You can view some conceptualizations for Phase II of the preservation of the Morris Island Lighthouse. Plans were provided by the contractor, Palmetto Gunite.

Page 1 shows the layout for the new micro-piles that were installed around the perimeter of the lighthouse foundation. There were a total of 68 micro-piles installed at 75 tons each capacity.

Page 2 shows the actual location of the micro-piles and how they were spaced around the foundation. All of the work was inside of the cofferdam installed in 2008.

Page 3 shows an elevation view of the new piles in relation to the original piles. The new piles were installed into the marl layer under the lighthouse. The area between the cofferdam and the foundation was filled with sand and capped with stone.

For photos of the preservation construction, see the photo gallery below.

March 1, 2010, we awarded our Phase II contract to Palmetto Gunite Construction Company, Ravenel, SC, for just under $2 million. This was a design/build contract to install new concrete piles under the foundation. This contract also filled the inside of the Phase I cofferdam with sand to help stabilize the foundation. The installation of 68 new micro-piles rated at 75 tons each was completed a month ahead of schedule. The jack-up barge pulled away on July 31, 2010.

This work will surely stabilize the tower so that we can continue to restore and preserve it in subsequent phases.

We survived Hurricane Irene. The Army Corps of Engineers requires periodic inspections.

Get in Touch

Get in Touch